FIELD: mining.
SUBSTANCE: invention relates to mining industry, preparation and development of stratified deposits. Method for preparation of excavation site in chamber development system includes division of mine field into working areas, driving of extraction galleries strata, connection of their inclination. First driving extraction galleries upper formation, then developed chamber upper formation. Alignment of upper chamber to pass slope of soil of lower reservoir, and end its deadlock horizontal workings. Passing excavation drifts of lower reservoir, and on bottom board and processing first chamber adjacent to chamber which passed in alignment of slope. Further, mined chamber connected to blind horizontal opening, which ends with a slope. Slope from upper layer to lower layer extends at an angle to ensure free movement of vehicles, while production of dead-end horizontal pass to a length equal to self-propelled equipment.
EFFECT: invention allows for preservation of integrity of inter-chamber pillars and reduces loss of minerals due to bias of penetration within treatment chamber.
3 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF COMBINED DEVELOPMENT OF CONTIGUOUS FORMATION OF DIFFERENT THICKNESSES | 2013 |
|
RU2532945C1 |
METHOD FOR CHAMBER MINING WHEN PREPARING HORIZONS | 2016 |
|
RU2627803C1 |
METHOD OF PREPARATION AND MINING CONTIGUOUS FLAT SEAMS | 2013 |
|
RU2530102C1 |
PROCESS OF DEVELOPMENT OF THICK GENTLY DIPPING COAL FORMATIONS WITH ROOF ROCKS DIFFICULT TO FALL | 2002 |
|
RU2219341C1 |
METHOD OF SLANT COAL SEAMS DEVELOPMENT | 1994 |
|
RU2068498C1 |
METHOD OF PREPARATION AND DEVELOPMENT OF EXTRACTION UNIT BY DIAGONAL CHAMBERS | 2019 |
|
RU2709266C1 |
EXCAVATION METHOD OF THICK FLAT-LYING COAL SEAM WITH FAST ROOF | 2006 |
|
RU2327037C1 |
METHOD OF MINING BED MINERAL DEPOSITS | 0 |
|
SU1752957A1 |
METHOD OF DEVELOPING THICK ORE DEPOSITS BY UNDERGROUND MINING WITH INTERCHAMBER PILLARS SUPPORT | 2009 |
|
RU2405109C1 |
METHOD FOR REMOVAL FIELD PREPARATION IN CASE OF CHAMBER-COLUMNAR EXCAVATION SYSTEM | 2003 |
|
RU2229599C1 |
Authors
Dates
2016-03-20—Published
2015-02-02—Filed