FIELD: mining.
SUBSTANCE: primary interchamber pillars are treated only after consolidation of a filling material with rocks of interchamber pillars, formed during primary treatment of a salt bed, when subsidence of the earth surface reaches ≥90% of the value of final subsidence of the earth surface from deformation of primary chambers, determined by observations along reference lines. The secondary treatment of the bed is started from the section of its deepest submersion, at the same time flattening of a shift mould formed during its secondary treatment is carried out by transfer of a treatment border from a border of primary treatment to the distance equal to the width of a softening zone, determined depending on environmental and mining conditions of the treated section.
EFFECT: invention makes it possible to increase extraction of a mineral due to involvement of a mineral left in a mineral into treatment.
3 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR DEVELOPMENT OF FLAT SEAMS OF MINERALS | 1995 |
|
RU2083834C1 |
METHOD OF MINING FLAT SEAMS AT ROOF CONTROL ON BAND PILLARS | 1994 |
|
RU2074959C1 |
METHOD OF ROOF CONTROL IN FLAT POTASSIUM SEAMS | 1994 |
|
RU2074960C1 |
METHOD FOR CONTROL OF ROCK PRESSURE | 1995 |
|
RU2081316C1 |
METHOD FOR EXTRACTING A BED OF SHALE | 2005 |
|
RU2287686C1 |
METHOD FOR EXTRACTING SALT DEPOSITS | 2003 |
|
RU2235879C1 |
METHOD FOR WORKING STARTA OF GENTLY SLOPING AND CLOSE FORMATIONS OF WATER-SOLUBLE MINERALS | 0 |
|
SU1038481A1 |
METHOD OF MINING OF WATER-BEARING DEPOSITS OF WATER-SOLUBLE MINERALS | 1999 |
|
RU2163297C1 |
METHOD FOR MINING OF GENTLY DIPPING CONTIGUOUS POTASSIUM BEDS | 1995 |
|
RU2099526C1 |
METHOD FOR UNDERGROUND DEVELOPMENT OF SALT BEDS | 2009 |
|
RU2403388C1 |
Authors
Dates
2012-11-27—Published
2011-07-26—Filed