FIELD: construction.
SUBSTANCE: method includes driving of a casing pipe for depth of not less than the depth of seasonal freezing-thawing of soil. Drilling of the pilot hole for depth of at least the normative value of soil freezing. Drilling of soil from the casing pipe cavity. Pouring of the hardening material in the volume necessary for filling of cavities between the pilot hole and the pile from the bottom of the pilot hole to the bottom of the level of the layer of seasonal freezing - thawing of soil. Submersion of a tubular pile into the pilot hole with a mortar. Filling of the cavity between the pile and casing pipe with non-swelling loose inert material.
EFFECT: increased bearing capacity of driven cast-in-situ piles.
5 cl, 1 dwg
Title | Year | Author | Number |
---|---|---|---|
PILE FOUNDATION FOR ARRANGEMENT OF SUPPORTS OF OVERHEAD POWER TRANSMISSION LINE | 2014 |
|
RU2556588C1 |
ARRANGEMENT METHOD OF SUPPORTS OF OVERHEAD POWER TRANSMISSION LINES ON PERMANENTLY FROZEN SOILS | 2014 |
|
RU2556589C1 |
COMBINED METHOD OF ARRANGEMENT OF PILE FOUNDATIONS IN PERMAFROST SOILS | 2019 |
|
RU2712976C1 |
METHOD TO ERECT PILE IN SEASONALLY FREEZING HEAVING SOILS | 2011 |
|
RU2474652C1 |
METHOD OF CONTROLLING POSITION OF ABOVE-GROUND PIPELINES UNDER PERMAFROST CONDITIONS | 2014 |
|
RU2582428C2 |
PILE AND METHOD OF ITS INSTALLATION INTO PERMAFROST SOIL | 2010 |
|
RU2441116C1 |
POLE FOR OVERHEAD SYSTEM TO BE ERECTED IN HEAVING GROUND | 2006 |
|
RU2317375C2 |
METHOD TO CONTROL NORMAL HEAVING FORCE ACTING IN DIRECTION OPPOSITE TO TANGENT HEAVING FORCE ACTION | 2006 |
|
RU2318097C1 |
METHOD OF CONSTRUCTION AND INSTALLATION OF PILES IN PERMAFROST ZONES USING HEAT STABILIZATION COUPLINGS | 2023 |
|
RU2818341C1 |
HEATED LOW-RISE BUILDING WITH FLOOR BY WARMED PEDIMENTAL CEILING SCAFFOLDING ON HEAVING GROUND BASE | 2006 |
|
RU2337211C2 |
Authors
Dates
2015-06-27—Published
2014-03-20—Filed