FIELD: oil and gas industry.
SUBSTANCE: method is suggested to determine whether well isolation operation is made accurately, and it includes the following stages: tubular casing is placed in the well borehole with at least one pressure sensor contained in its wall and faced to circular area concluded between outer surface of the above tubular casing and inner surface of the well borehole or between outer surface of the above tubular casing and inner surface of the other tubular casing containing the above tubular casing; well isolation operation is carried out in the above circular area, at that during operation performance a packer is set in the circular area so that the packer sealing component is thrust hermetically into the casing pipe with the above tubular casing or to the wall of the well borehole. Further the method includes the stage whereat pressure of fluid in the circular area is controlled during well isolation operation by means of the pressure sensor and data on fluid pressure in the circular area downstream the well borehole in regard to the sealing component are transmitted, at that pressure drop detected with time in the circular area downstream the well borehole in regard to the sealing component specifies available loss behind the packer. The tubular casing used for the method implementation is also described.
EFFECT: control of the packer setting in the well is provided.
41 cl, 12 dwg
Title | Year | Author | Number |
---|---|---|---|
DRILL STEM EQUIPMENT WITH INTEGRATED RING BARRIER AND COLLAR WITH HOLE, METHOD AND SYSTEM | 2014 |
|
RU2663832C1 |
WELL CONSTRUCTION AND OPERATION METHOD | 2005 |
|
RU2320849C2 |
METHOD AND DEVICE FOR DRILLING AND COMPLETION AT PROGRAMMED PRESSURE AND PROGRAMMED PRESSURE GRADIENT | 2008 |
|
RU2455453C2 |
WELL COMPLETION IN ONE PRODUCTION STRING RUNNING | 2003 |
|
RU2349735C2 |
METHOD FOR LOCATING TRIP CEMENTING PLUG IN CASING STRING. | 2022 |
|
RU2805636C1 |
METHOD FOR DETERMINATION OF TIGHTNESS OF COLUMN AND SHANKS | 2019 |
|
RU2730228C1 |
METHOD OF PHYSICAL ABANDONMENT OF WELLS | 2014 |
|
RU2576422C1 |
PLACING A FLUID COMPRISING KILN DUST IN A WELLBORE THROUGH A BOTTOM HOLE ASSEMBLY | 2014 |
|
RU2657276C1 |
EQUIPMENT AND OPERATIONS OF MOVABLE INTERFACE UNIT | 2014 |
|
RU2645044C1 |
DOWNHOLE TESTING METHOD IN OPEN HOLE | 2016 |
|
RU2625126C1 |
Authors
Dates
2015-11-10—Published
2012-05-16—Filed