FIELD: mining industry.
SUBSTANCE: invention can be used in potash industry for reclamation of salt dump slopes. The method includes forming a support prism from fresh salt waste at the bottom of the salt dump slope, then filling it with a levelling layer from fresh salt waste at an angle of their natural repose, followed by installation of a waterproof coating over the levelling layer and the support prism. The levelling layer of salt waste on the slope of the salt dump is poured to the width of the upper platform of the support prism. The support prism is made with a stepped lowering of its base away from the salt dump. The waterproof coating consists of two layers of drainage mats made of geosynthetic materials and a layer of waterproofing material between them.
EFFECT: increase of efficiency of protection of salt dumps from the effects of atmospheric precipitation and reduction of excess brine, ensuring levelling of the surface of the salt dump ensuring integrity of the waterproofing coating.
4 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR DISCHARGE OF SALT DISPOSAL WASTE DURING ITS RECULTIVATION | 2023 |
|
RU2797225C1 |
METHOD FOR RECLAMATION OF SALT TAILINGS PILE | 2017 |
|
RU2654102C1 |
METHOD OF WATERPROOF COATING INSTALLATION ON SLOPES OF SALT-SEAM | 2018 |
|
RU2687716C1 |
METHOD OF SLUDGE DUMP LOCATION ON THE TERRITORY OF FUTURE SALT DUMPS | 2015 |
|
RU2597237C1 |
METHOD FOR RECLAIMING SLOPES SALT DUMPS | 2014 |
|
RU2584711C1 |
METHOD FOR RECLAMATION OF SALTDUMP SLOPES | 0 |
|
SU1652570A1 |
METHOD OF DEPOSITING WASTE OF CONCENTRATION MILLS OF POTASSIUM WORKS | 0 |
|
SU994727A1 |
METHOD FOR SALT DUMP AND MUD PIT CONSTRICTION IN SINGLE AREA | 2006 |
|
RU2316651C1 |
METHOD OF DUMPING OF POTASSIUM ORE CONCENTRATION WASTES ON SOFT BASE | 2001 |
|
RU2204717C1 |
METHOD FOR ARRANGEMENT OF POTASSIUM PLANTS DRESSING WORKS WASTES | 2009 |
|
RU2402682C1 |