FIELD: welding technology.
SUBSTANCE: invention relates to fixtures and devices for manufacturing, assembly, and welding of metal products. A method for manufacturing welded polyhedral piles involves manufacturing a pile body from rolled sheets by bending. The locking elements are installed, fixed and secured to the pile body by welding. At least two devices are installed along the length of the pile. Each device contains clamps equipped with hinged eyes and connected to each other by a screw tie. The pile body is installed on the mounting plate with the bottom part. Locking elements are installed on the end faces of the pile body. Using a screw tie of the devices, the distance between the clamps is set in accordance with the current position of the locking elements. The locking elements are fixed on the end faces of the pile body with clamps. The design distance is set between the locking elements. The locking elements are welded to the body of the pile. The pile is cooled in the air to a temperature of the welds and heat-affected zone not exceeding 200 °C.
EFFECT: minimized deformation of the pile during welding.
1 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF COLUMNS ASSEMBLY AND DEVICE FOR COLUMNS GRIPPING | 2006 |
|
RU2334067C1 |
TRANSPORT-LAUNCHING PACK FOR ROCKETS AND METHOD OF ITS MANUFACTURE | 2000 |
|
RU2166166C1 |
GANTRY OF LOAD-LIFTING DEVICE | 0 |
|
SU1648885A1 |
PILING WALL | 2018 |
|
RU2708330C1 |
METHOD OF BUTT JOINTING OF CEILING PLATES WITH COLUMN AND DEVICE FOR ITS IMPLEMENTATION | 2007 |
|
RU2334060C1 |
PROTECTIVE CASE FOR BRIDGE PIER GRILLAGE AND ERECTION METHOD THEREOF | 2004 |
|
RU2263176C1 |
SHEET PILE | 2023 |
|
RU2818614C1 |
MULTI-PURPOSE PRODUCTION LINE FOR ELONGATED BUILDING STRUCTURE PRODUCTION, ELONGATED BUILDING STRUCTURE, GIRDER AND LARGE-SPAN BEAM TO BE PRODUCED WITH THE USE OF THE LINE | 2005 |
|
RU2315693C2 |
METHOD OF ERECTING TONGUE-AND-GROOVE ENCLOSURE DURING MAIN PIPELINE OPERATIONS AND SHEET COLLAPSIBLE ENCLOSURE FOR CONSTRUCTION OF PIT | 2018 |
|
RU2705674C2 |
METHOD FOR MANUFACTURE OF HALF-TRACKS OF MECHANIZED DOUBLE-TRACK DOUBLE-SECTION SPAN STRUCTURE OF BRIDGE UNIT | 1995 |
|
RU2102553C1 |
Authors
Dates
2024-02-15—Published
2023-03-31—Filed