FIELD: mining.
SUBSTANCE: invention relates to a method of performing repair and insulation works in a well. According to the method, a module with hydraulic cylinders mounted on a tubing string and connected to a packer-plug, which includes a fixed shaft and movable parts, is installed at the wellhead and then lowered into the well. When a given depth is reached, a ball is thrown into the tubing string and excess pressure is created in the tubing string, as a result of which the hydraulic cylinders move downward relative to the fixed shaft and exert a force effect on the movable parts of the packer-plug, ensuring its installation in the well and isolating the required interval. In case of insufficient hydraulic connection of the well with the casing string above the place of installation of the packer-plug, intermediate lowering of the piercing perforator is performed on the tubing string to create a puncture of the production string. Then module with hydraulic cylinders and filling packer-retainer, including fixed shaft and movable parts, is lowered to tubing. When the pre-set depth is reached, excess pressure is created in the tubing, as a result of which the hydraulic cylinders move downwards relative to the fixed shaft and exert a force effect on the movable parts of the filling packer-retainer. Then, insulating material in the form of a cement composition is poured through the installed filling packer-retainer under pressure with its guaranteed penetration through the holes made by the piercing perforator.
EFFECT: improving efficiency, versatility and safety of repair and insulation works in wells, reducing time and labour costs, expansion of technological potential.
1 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
WATER AND GAS INFLUX LIMITING METHOD WITH WELL PRODUCTIVITY RECOVERY | 2013 |
|
RU2539047C1 |
METHOD FOR ISOLATING WATER INFLOWS IN GAS WELLS WITH A SUB-HORIZONTAL WELLBORE END | 2022 |
|
RU2794105C1 |
METHOD OF BOTTOM WATER CONE CUTTING | 2016 |
|
RU2655490C2 |
METHOD FOR ELIMINATING FLOWS BEHIND THE CASING IN PETROLEUM PRODUCTION BOREHOLES | 2021 |
|
RU2774251C1 |
PROCEDURE FOR ISOLATING OPERATIONS IN WELL AND PACKER EQUIPMENT | 2010 |
|
RU2414586C1 |
METHOD FOR MULTIPLE HYDRAULIC FRACTURING OF FORMATION IN HORIZONTAL BOREHOLE OF WELL | 2019 |
|
RU2708747C1 |
METHOD FOR ISOLATION OF WATER FLOW IN OPEN HORIZONTAL SECTION PRODUCING WELLS | 2014 |
|
RU2578095C1 |
METHOD OF PREVENTING WATER FLOW IN WELL DEVELOPED OIL IN WATER RESERVOIR | 2017 |
|
RU2665769C1 |
METHOD FOR CASING PIPE LEAKAGE INTERVAL ISOLATION INSIDE WELL | 2006 |
|
RU2317399C1 |
METHOD FOR REPAIR AND ISOLATION WORK IN WELLS | 1991 |
|
RU2053357C1 |
Authors
Dates
2024-09-23—Published
2023-12-29—Filed