METHOD FOR CYCLIC MOVEMENT OF SOLID REINFORCED CONCRETE BRIDGE SPAN IN LONGITUDINAL DIRECTION Russian patent published in 2004 - IPC

Abstract RU 2242559 C1

FIELD: building, particularly erection of preloaded reinforced concrete span structure having different span types and cross-sections.

SUBSTANCE: method is used for erecting span structure above existent buildings, structures, service lines, deep ravines and other barriers arranged along bridge axis. Bridge has side walls or ribs, upper or lower plates and straight reinforcement arranged in upper plate and located from inner surface of side walls or ribs. Method of bridge movement to piers involves concreting span structure sections in concrete form; reinforcing thereof and connecting the first one of formed sections to launching nose having length equal to 50%-60% of that of span structure section to be connected with it; moving above section by push jack and connecting next sections; arranging tightened through bundle of reinforcement in side walls thereof and in ribs after all span structure sections installation in design position; connecting reinforcement of all span structure sections. Form is made of two parts having sliding blocks, namely the first, lower, block supported by four hydraulic jacks and used for concreting lower plate, and the second block used for concreting side walls or ribs and upper plate. Section form is arranged behind push jacks along one concreting section. Launching nose is connected to front span structure section by means of single strands tightened by single-strand jacks. Movement is carried out with the speed of 7.5-12.5 m/h with push jack force not exceeding half of vertical force created by lifting jacks additionally used for span structure section movement. Length of through reinforcement bundle is not less than summary length of three span structure sections.

EFFECT: reduced time for bridge building and carrying out special supplementary works in spans.

3 dwg

Similar patents RU2242559C1

Title Year Author Number
CONSTRUCTION METHOD FOR BRIDGE OR OVERPASS 2002
RU2251604C2
MONOLITHIC SOLID PRESTRESSED PLATE-AND-RIB BRIDGE SPAN STRUCTURE 2004
  • Monov B.N.
  • Matechenkov V.P.
  • Illarionov A.V.
  • Safonov A.V.
  • Raevskaja Ju.I.
  • Borovskikh L.D.
  • Konopel'Ko T.I.
  • Ponomarev B.V.
RU2249068C1
METHOD FOR ERECTION OF CONTINUOUS STEEL-REINFORCED CONCRETE SUPERSTRUCTURE OF BRIDGE WITH MONOLITHIC REINFORCED CONCRETE SLAB 2020
  • Utkin Vladimir Aleksandrovich
RU2737771C1
METHOD FOR CONSTRUCTION OF REINFORCED CONCRETE DECK INTERSECTION WITH LARGE SPAN 2013
  • Shamanina Natal'Ja Pavlovna
  • Kljanchenkov Anatolij Ivanovich
  • Molev Aleksandr Aleksandrovich
  • Volkov Vladimir Andreevich
RU2522712C1
CONSTRUCTION METHOD AND DESIGN OF OVERPASSES AND BRIDGES UNDER CONDITIONS OF PERMAFROST 2012
  • Bikbau Marsel' Janovich
  • Bikbau Ul'Jana Marsel'Evna
RU2513574C2
METHOD FOR REINFORCED CONCRETE BRIDGE CONSTRUCTION 2004
  • Fajko Jurij Ivanovich
RU2283911C2
METHOD OF ERECTING MONOLITHIC REINFORCED CONCRETE SPAN OF BRIDGE BY PUSHING 0
  • Krylov Vyacheslav Aleksandrovich
  • Loginov Valentin Georgievich
  • Yanovskij Grigorij Matveevich
  • Rogozhin Vladimir Mikhajlovich
SU619560A1
PRESTRESSED FERROCONCRETE CONSTRUCTIONS 1997
  • Zakharov Eh.V.
  • Klonitskij M.L.
  • Belokhin S.L.
  • Khaustov I.M.
RU2131010C1
METHOD FOR MANUFACTURING A GRAVITY-TYPE BASE (GTB) AT A SPECIALIZED PRODUCTION SITE 2022
  • Mikhelson Leonid Viktorovich
  • Retivov Valerii Nikolaevich
  • Solovev Sergei Gennadevich
RU2771197C1
METHOD OF MOUNTING AN UNSPLIT STEEL-FERROCONCRETE BRIDGE SPAN STRUCTURE 0
  • Dankov Valerij Sergeevich
  • Datskovskij Vladimir Modestovich
SU1333736A1

RU 2 242 559 C1

Authors

Kurakin P.P.

Korotin V.N.

Chalenko V.V.

Dudarev S.V.

Melkonjan A.S.

Birjukov E.N.

Potapov S.V.

Dates

2004-12-20Published

2004-02-19Filed