FIELD: pipeline transport; laying of underground pipelines.
SUBSTANCE: according to proposed method, trench is dug in tectonic fracture sections and trays are placed in trench, then pipeline is placed on trays on hangers and tray are covered by plates. Support members with cradles suspended from trays on wire ropes are laid on sides of trays at definite distances from each other. Said cradles are made of section of pipe, and pipeline is placed on said cradles.
EFFECT: facilitated laying of pipeline in trays.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ERECTION OF UNDERGROUND PIPELINE AT CROSSING OF TECTONIC FRACTURES | 2008 |
|
RU2363875C1 |
METHOD FOR ERECTION OF UNDERGROUND PIPELINE AT CROSSING OF TECTONIC FRACTURES | 2008 |
|
RU2363876C1 |
METHOD OF LAYING PIPELINES OVER TECTONIC FAULT | 2004 |
|
RU2264577C1 |
METHOD OF CONSTRUCTING BURIED PIPELINE IN CROSSING SECTION WITH FORECAST CONCENTRATED DEFORMATIONS OF ENCLOSING STRATA | 2011 |
|
RU2460926C1 |
METHOD OF CONSTRUCTION OF UNDERGROUND PIPELINE IN SECTION OF TECTONIC FAULTS | 2000 |
|
RU2197667C2 |
METHOD OF LAYING UNDERGROUND PIPELINE | 2003 |
|
RU2256839C2 |
CONSTRUCTION METHOD OF UNDERGROUND PIPELINE AT INTERSECTION OF TECTONIC BREAKS | 2008 |
|
RU2365802C1 |
METHOD FOR ERECTION OF UNDERGROUND PIPELINE AT CROSSING OF TECTONIC FRACTURES | 2008 |
|
RU2363874C1 |
UNDERGROUND PIPELINE FOR SEISMIC ZONES | 2001 |
|
RU2241889C2 |
METHOD OF PROTECTING UNDERGROUND PIPELINES IN SEISMICALLY-ACTIVE ZONES | 2004 |
|
RU2251043C1 |
Authors
Dates
2005-10-20—Published
2003-09-03—Filed