FIELD: bridge construction, particularly reinforced concrete, steel and composite bridge, bridge span structure and overpass repair and reconstruction.
SUBSTANCE: method to reconstruct beam bridge including at least two span structures involves disassembling span structures; substituting span structures for earth-filled arch structure and installing beam bridge on truncated piers. Each span structure is substituted for one semi-arch. Central beam bridge supports are left as they are or treated to impart T or V shape thereto or additional central and extreme piers are installed. Piers are truncated from opposite central pier sides. Base of each semi-arch is connected to truncated piers. Semi-arch top is fastened to non-truncated pier. Existent piers are truncated up to erection site level. Other vacant piers of span structure are truncated to provide assemblage and earth-filling operations to repair bridge and road paving. Semi-arches are formed of corrugated metal or reinforced concrete.
EFFECT: possibility to reconstruct bridges crossing narrow rivers along with maintaining of water current flow volume within the previous scope, possibility to use existent pile base.
5 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
PROCESS OF RECONSTRUCTION OF BEAM BRIDGE | 2003 |
|
RU2225912C1 |
METHOD FOR DISASSEMBLY OF ARCH BRIDGE | 2022 |
|
RU2800582C1 |
RING HIGHWAY OF MEGAPOLICE AND METHOD FOR ITS RECONSTRUCTION | 1998 |
|
RU2136803C1 |
METHOD FOR RECONSTRUCTION OF OVERPASS WITH DISPLACEMENT OF RECONSTRUCTED RAILWAY BRIDGE AFLOAT | 1999 |
|
RU2152477C1 |
TRANSPORT COMPLEX OF MEGALOPOLIS AND METHOD FOR CONTROL AND RELIEF OF PASSENGER, FREIGHT - PASSENGER AND FREIGHT TRAFFICS OF MEGALOPOLIS TRANSPORT COMPLEX | 1998 |
|
RU2140480C1 |
TRANSPORTATION COMPLEX OF MEGAPOLICE AND METHOD FOR REGULATING AND RELIEVING PASSENGER, CARGO-PASSENGER AND CARGO TRAFFIC FLOWS IN IT | 1998 |
|
RU2135670C1 |
METHOD FOR RECONSTRUCTION OF PRESTRESSED REINFORCED CONCRETE BOX-SHAPED STRUCTURE | 2022 |
|
RU2801995C1 |
MEGAPOLICE RING HIGHWAY AND METHOD FOR ITS RECONSTRUCTION | 1998 |
|
RU2136802C1 |
GROUND FILLING BRIDGE | 2023 |
|
RU2822619C1 |
METHOD FOR TRANSFER OF LONG-SPAN STEAM-AND-WATER MIXTURE DELIVERY PIPELINE OVER CANYON LOCATED IN SEISMICALLY ACTIVE ZONE | 2023 |
|
RU2815705C1 |
Authors
Dates
2007-07-10—Published
2005-11-25—Filed