FIELD: construction, particularly to erect industrial and civil buildings on collapsible soil characterized by non-uniform settlement in karstic territories.
SUBSTANCE: method involves creating through nozzles in foundation body; filling the nozzles with working body and connecting ground pump to each nozzle flange; providing eccentrically compressed column stanchions with support T-bars connected with foundation through anchoring bolts, wherein the anchoring bolts have fastening nuts arranged from top part thereof and support straightening nuts located under support T-bar; arranging nozzles so that nozzle flared mouths extend in foundation bottom and side edges; connecting ground pumps provided with double-acting impulse hydraulic jacks with nozzle flanges; switching-on hydraulic jacks; injecting and pressing working body in nozzles with the use of said jet engines and creating jet thrust by working body jet flowing from nozzles; extruding working body from nozzles under foundation and controlling foundation displacement by jet engines; providing upward foundation movement to press-out and pull-out foundation from ground base up to design mark; intruding and introducing working body in weakened ground base zones under foundation and consolidating ground base in weakened zones; extruding working body from nozzles in backward direction and imparting forward movement to foundation; extruding working body from nozzles in forward direction and imparting backward movement to foundation; extruding working body from nozzles to the right and providing foundation movement to the left; extruding working body from nozzles to the left and providing foundation movement to the right; restoring design foundation position; stopping reactive foundation movement control by switching-off engines; retaining working body in nozzles and fixing foundation in design position.
EFFECT: possibility to control spatial building structure position, provision of design foundation position recovery, prevention of building inclination and settlement.
3 dwg
Title | Year | Author | Number |
---|---|---|---|
FOUNDATION FOR ECCENTRIC LOADED COLUMN | 2002 |
|
RU2225480C2 |
METHOD TO CONTROL STRESSED STATE OF DOUBLE-SPAN BUILDING FRAME WITH THE USE OF FOUNDATIONS WITH JET ENGINES | 2005 |
|
RU2319811C2 |
METHOD TO ELIMINATE STRUCTURE INCLINATION WITH THE USE OF REACTIVE BUTTRESSES | 2005 |
|
RU2299952C2 |
METHOD TO CONTROL DISPLACEMENT, SETTING AND HEELING OF STRUCTURE BY PILED FOUNDATIONS, BEING MACROREGULATORS | 2008 |
|
RU2416696C2 |
DREDGE PUMP | 2002 |
|
RU2228408C2 |
METHOD TO AVOID COLLAPSE OF METAL STRUCTURES OF FRAME BECAUSE OF FIRE | 2009 |
|
RU2411330C1 |
DOUBLE-SPAN BUILDING FRAME | 2005 |
|
RU2319817C2 |
CONNECTION UNIT FOR TWO-LEG ECCENTRICALLY LOADED COLUMN WITH FOUNDATION AND METHOD FOR RESTORING DESIGN LEVEL OF FOUNDATION AND BUILDING FRAME | 2002 |
|
RU2236508C2 |
PROCEDURE CONTROLLING LIST AND SINKING OF SOLID MASS STRUCTURE | 2001 |
|
RU2211288C2 |
HYDRAULIC JACK LIFTING POWER BOOSTER | 2006 |
|
RU2325484C2 |
Authors
Dates
2008-03-20—Published
2006-02-13—Filed