METHOD OF FOUNDATION BED CONSTRUCTION BY HORIZONTAL REINFORCING WITH PRECAST CONCRETE COMPONENTS Russian patent published in 2009 - IPC E02D27/01 

Abstract RU 2344231 C1

FIELD: construction.

SUBSTANCE: invention relates to foundation construction technologies, and particularly, to reinforcing technology used for compressible foundation sections of detached or slab-shaped foundations in building and structures being erected under severe engineering and geological and hydro-geological conditions. Method of foundation bottom construction by horizontal reinforcing with precast concrete components includes foundation pit mining and installation of horizontal stiff lengthy elements such as crossties. As soon as the foundation pit is developed to the designed depth and is bladed, the foundation pit bottom is leveled and filled with sand or crushed stone generating underlying layer with the designed thickness being no less than 0.05 m. Then this layer is leveled and compacted. After that, foundation axes and longitudinal axes of crossties are broken down regarding foundation axes and against the established construction layout depending on the foundation type of the structure being built. The crossties are laid down above the underlying layer in such a way to produce crosstie distribution element in the compressible section in accordance with the designed construction layout of longitudinal crosstie axes with regard to foundation axes. The crossties are installed so that their beds coincide with the level of underlying layer of foundation pit. In addition, crossties are installed butt to each other so that total length of each crosstie exceeds the distance between the external shapes of the utmost foundation edges of the building. The crossties are laid parallel to each other at the design distance so that the area of crosstie distributing element overlaps foundations area completely. Then, inter-crosstie space is filled with sand and buffer layer is laid from above to the level of foundation bed installation with sand, crushed stone from solid rocks or crushed stone from ferrous metallurgy wastes. The buffer layer thickness must not be less than 1/3 of crosstie width or cross section diameter. Maximum size of crushed stones must not exceed 1/5 of crosstie width or cross section diameter. The foundation pit is mined to the design depth, which is equal to sum of future foundation bed depth, buffer layer thickness, crosstie cross section height or diameter and underlying layer thickness.

EFFECT: improvement of soft ground foundations bearing capacity and reduction of material consumption.

2 cl, 4 dwg

Similar patents RU2344231C1

Title Year Author Number
METHOD OF FOUNDATION BED CONSTRUCTION BY HORIZONTAL REINFORCING WITH SOLID CONCRETE COMPONENTS 2007
  • Saurin Anatolij Nikiforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Zhadanovskij Boris Vasil'Evich
  • Kuznetsova Ekaterina Anatol'Evna
  • Saurin Jaroslav Anatol'Evich
  • Red'Kina Julija Vjacheslavovna
  • Miljutin Denis Nikolaevich
RU2344232C1
METHOD TO ARRANGE BASE OF STRUCTURAL FOUNDATIONS 2012
  • Saurin Anatolij Nikiforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Saurin Jaroslav Anatol'Evich
RU2496944C1
METHOD FOR RECOVERY OF EXHAUSTED OPEN PITS FOR CONSTRUCTION OF STRUCTURES 2009
  • Boldyrev Oleg Valentinovich
  • Mukhortov Vasilij Vasil'Evich
  • Neljubin Igor' Viktorovich
  • Olejnik Sergej Pavlovich
RU2387837C1
METHOD OF DANGEROUS AND RECONSTRUCT ABLE BUILDING FOUNDATIONS REINFORCEMENT 2002
  • Saurin A.N.
  • Bagdasarov Ju.A.
  • Zhadanovskij B.V.
  • Firsov A.N.
  • Karavashkin N.N.
RU2229562C1
METHOD OF COMBINED IN SITU PILE MANUFACTURING 2007
  • Saurin Anatolij Nikoforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Zhadanovskij Boris Vasil'Evich
  • Saurin Jaroslav Anatol'Evich
  • Red'Kina Julija Vjacheslavovna
  • Miljutin Denis Nikolaevich
RU2334049C1
METHOD OF MANUFACTURING OF BEARING COMBINED REINFORCED IN SITU PILE 2007
  • Saurin Anatolij Nikiforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Zhadanovskij Boris Vasil'Evich
  • Saurin Jaroslav Anatol'Evich
  • Red'Kina Julija Vjacheslavovna
  • Miljutin Denis Nikolaevich
RU2334048C1
METHOD OF CAST-IN-PLACE PILE CONSTRUCTION OUT OF SOIL AND SLAG MIX WITH SOLIDIFICATION ACTIVATING AGENT IN EXPANDED WELLS 2007
  • Saurin Anatolij Nikiforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Zhadanovskij Boris Vasil'Evich
  • Saurin Jaroslav Anatol'Evich
  • Red'Kina Julija Vjacheslavovna
  • Miljutin Denis Nikolaevich
RU2354780C1
METHOD OF MANUFACTURING OF CHIPPING IN SITU PILE 2007
  • Saurin Anatolij Nikiforovich
  • Il'Ichev Vjacheslav Aleksandrovich
  • Zhadanovskij Boris Vasil'Evich
  • Saurin Jaroslav Anatol'Evich
  • Red'Kina Julija Vjacheslavovna
  • Miljutin Denis Nikolaevich
RU2338032C1
METHOD OF RECOVERING BARROW PITS FOR COSTRUCTING VARIOUS STRUCTURES 2007
  • Boldyrev Oleg Valentinovich
  • Neljubin Igor' Viktorovich
  • Mukhortov Vasilij Vasil'Evich
  • Nemtsev Petr Sergeevich
  • Morozov Gennadij Sergeevich
  • Olejnik Sergej Pavlovich
RU2354830C1
SHALLOW FOUNDATION STRUCTURE 2015
  • Lishchuk Petr Nikiforovich
RU2605470C2

RU 2 344 231 C1

Authors

Saurin Anatolij Nikiforovich

Il'Ichev Vjacheslav Aleksandrovich

Zhadanovskij Boris Vasil'Evich

Kuznetsova Ekaterina Anatol'Evna

Saurin Jaroslav Anatol'Evich

Red'Kina Julija Vjacheslavovna

Miljutin Denis Nikolaevich

Dates

2009-01-20Published

2007-12-03Filed