FIELD: railway transport.
SUBSTANCE: proposed method comprises laying rail 12 onto sub rail gasket 10 of metal pad 2 so that axes of rail 12 and pad 10 are aligned, while metal pad axis 2 is shifted by 4 mm relative to rail axis. Rails worn out, metal pad 2 is relieved to be turned through 180°, rail 12 is shifted to rated standard track gauge. Axis of metal pad 2 should be shifted relative to rail 12 by 4 mm. Metal pad 2 has two flanges 11 and sub rail gasket 10 with axis of metal pad 2 shifted relative to axis of sub rail gasket 10 by 4 mm.
EFFECT: higher reliability of rail joint.
2 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
BOLTLESS RAIL FIXTURE AND RAIL PAD OF BOLTLESS RAIL FIXTURE | 2012 |
|
RU2493311C1 |
RAIL FASTENING | 2001 |
|
RU2216619C2 |
INTERMEDIATE RAIL FASTENING | 2023 |
|
RU2805596C1 |
RAIL FASTENING | 2001 |
|
RU2216620C2 |
ANCHOR CLIP-BOLT RAIL JOINT (VERSIONS) | 2011 |
|
RU2468133C1 |
RAIL FASTENING | 2016 |
|
RU2624765C1 |
RAIL FASTENING | 1996 |
|
RU2100510C1 |
METHOD OF PROLONGATION OF RAIL LENGTHS SERVICE LIFE | 1999 |
|
RU2153551C1 |
METHOD OF PREVENTING FRACTURES OF RAIL LENGTHS | 1999 |
|
RU2153552C1 |
RAIL FASTENER | 1998 |
|
RU2131954C1 |
Authors
Dates
2010-01-10—Published
2007-07-24—Filed