FIELD: construction.
SUBSTANCE: method for construction of underground structure includes arrangement of foundation grill along perimetre of planned pit and walls in soil with further working of pit. Wall in soil is piled, and in process of its arrangement piles are driven into foundation grill by method of static squeezing of piles down to project elevation, and additionally at least one underground tier of wall is erected, for this purpose soil is excavated under foundation grill along driven piles, then reinforcement frame is installed, and underground tier of wall is concreted, at the same time ratio of pit depth to driven part of piles must correspond to 0.30-0.36.
EFFECT: reduced labour intensiveness and material intensity in erection of underground structure, simplified erection of underground structure in restricted conditions of dense urban development.
2 cl, 1 tbl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD TO ERECT MULTISTORY SUBSURFACE STRUCTURE | 2009 |
|
RU2414563C1 |
METHOD TO ERECT RECESSED STRUCTURES AND UNDERGROUND STRUCTURES OF BUILDINGS | 2012 |
|
RU2491387C1 |
METHOD OF CONSTRUCTION OF UNDERGROUND STRUCTURE | 2022 |
|
RU2800171C1 |
PROCESS OF DEVELOPMENT OF FOUNDATION PIT | 2002 |
|
RU2209268C1 |
PROCESS OF ERECTION OF ENCLOSING WALL IN GROUND | 2001 |
|
RU2204656C1 |
PROCESS OF ERECTION OF MULTILEVEL UNDERGROUND STRUCTURE ( VARIANTS ) | 2003 |
|
RU2220258C1 |
METHOD OF INDUSTRIAL BUILDING FOUNDATION CONSTRUCTION | 2003 |
|
RU2244067C1 |
METHOD FOR STRUCTURE CONSTRUCTION IN THE UNDER-RUNNER SPACE OF RIVERS AND CANALS IN URBAN DEVELOPMENT | 2021 |
|
RU2770187C1 |
COMBINED (PILE-SLAB, PILE-BELT, PILE-COLUMNAR) FOUNDATION ERECTION METHOD | 2015 |
|
RU2667163C2 |
METHOD FOR BLOCK-MODULAR CONSTRUCTION OF STRUCTURES IN FOUNDATION PITS AND BURIED STRUCTURE FOR MILITARY INFRASTRUCTURE FACILITIES | 2018 |
|
RU2702779C1 |
Authors
Dates
2010-06-20—Published
2009-02-11—Filed