FIELD: construction.
SUBSTANCE: method for construction of heat resistant high-rise reinforced concrete pipes with low exit diametre with high thickness of heat insulation and lining of piece materials includes erection of pipe shaft using multi-cubicle shaft lift, lifting device that covers shaft lift and working platform moved along with curb for concreting of pipe shaft.
EFFECT: provision of possibility to construct heat resistant high-rise reinforced concrete pipes with low exit diametre with high thickness of heat insulation and lining of piece materials, reduced metal intensity, labour intensiveness, increased quality of works and safety of labour, improved labour conditions.
3 cl, 5 dwg
Authors
Dates
2010-12-10—Published