METHOD OF CONSTRUCTION USING MULTI-CAGE MINE HOIST OF HEIGHT REINFORCED CONCRETE PIPES WITH LARGE THICKNESS OF LINING WITH SMALL OUTLET DIAMETER AND LARGE RATIO OF OUTLET DIAMETER TO DIAMETER IN BASE Russian patent published in 2016 - IPC E04H12/28 

Abstract RU 2574226 C1

FIELD: construction.

SUBSTANCE: pipe construction is started from erection of a pipe shaft and installation of lining from one installation of the device for lifting of a working site, at the same time the sequence of pipe shaft concreting and lining installation is performed in two possible versions.

EFFECT: expanded range of typical sizes of constructed pipes to the possibility of their construction with larger lining thickness at small outlet diameter and with large ratio of diameter in a pipe base to outlet diameter with reduced material intensity, prime cost and increased efficiency.

19 dwg

Similar patents RU2574226C1

Title Year Author Number
METHOD TO USE MULTI-BASKET MINE HOIST FOR CONSTRUCTION OF REINFORCED CONCRETE HIGH-RISE PIPES WITH HIGH THICKNESS OF LINING, WITH SMALL OUTPUT DIAMETER AND WITH HIGH RATIO OF OUTLET DIAMETER TO DIAMETER IN BASE 2013
  • Shevljagin Boris Mikhajlovich
RU2544921C1
METHOD TO CONSTRUCT HIGH-RISE REINFORCED CONCRETE INDUSTRIAL PIPES WITH MULTI-LAYER LINING WITH SMALL OUTLET DIAMETER 2012
  • Shevljagin Boris Mikhajlovich
  • Frumkin Vjacheslav Moiseevich
RU2518601C2
METHOD FOR CONSTRUCTION OF HEAT-RESISTANT HIGH-RISE REINFORCED CONCRETE PIPES WITH LOW EXIT DIAMETRE WITH HIGH THICKNESS OF HEAT INSULATION AND LINING OF PIECE MATERIALS 2009
  • Shevljagin Boris Mikhajlovich
  • Frumkin Vjacheslav Moiseevich
  • Shevljagina Natalija Borisovna
RU2405897C1
METHOD OF CONSTRUCTION OF REINFORCED HIGH-RISE BUILDINGS WITH SMALL INNER DIAMETER, WITH SMALL SLOPE OF TRUNK AND LARGE WALL, FOR EXAMPLE OF SUPPORTING TOWERS AND MASTS 2016
  • Shevlyagin Boris Mikhajlovich
RU2658397C2
METHOD OF REPAIR AND RECONSTRUCTION OF TALL CHIMNEYS AND PARTIAL DISASSEMBLY OF SHAFT DURING THEIR RECONSTRUCTION 2001
  • Shevljagin B.M.
  • Frumkin V.M.
  • Gavrilov A.I.
  • Zhits G.N.
  • Zinov'Ev A.V.
  • Khod'Ko A.A.
RU2209282C1
METHOD OF ERECTING HIGH-RISE REINFORCED CONCRETE STRUCTURES, FOR EXAMPLE, INDUSTRIAL CHIMNEY-STACKS AND TOWERS 2011
  • Shevljagin Boris Mikhajlovich
  • Frumkin Vjacheslav Moiseevich
RU2476653C1
PROCESS OF REPAIR AND RECONSTRUCTION OF TALL INDUSTRIAL CHIMNEYS 2001
  • Frumkin V.M.
  • Shevljagin B.M.
  • Zakharov Ju.I.
  • Petrov V.G.
  • Mardukhaev I.N.
RU2209283C1
CONSTRUCTION METHOD OF HIGH-RISE REINFORCED CONCRETE BUILDINGS FOR EXAMPLE WITH INDUSTRIAL PIPES AND TOWERS OF SMALL INNER DIAMETRE 2008
  • Shevljagin Boris Mikhajlovich
  • Frumkin Vjacheslav Moiseevich
  • Shevljagina Natalija Borisovna
RU2380502C1
METHOD OF ERECTING HIGH FERROCONCRETE FLUES 0
  • Shevlyagin Boris Mikhajlovich
SU1441038A1
METHOD OF REPAIR AND RECONSTRUCTION OF HIGH-RISE REINFORCED CONCRETE STRUCTURES WITH VARIABLE TAPER, FOR INSTANCE, COOLING TOWERS AND INDUSTRIAL PIPES 2006
  • Shevljagin Boris Mikhajlovich
  • Frumkin Vjacheslav Moiseevich
RU2334068C2

RU 2 574 226 C1

Authors

Shevljagin Boris Mikhajlovich

Dates

2016-02-10Published

2014-09-02Filed