FIELD: engines and pumps.
SUBSTANCE: use of modules of compressor units of larger capacity is implemented at small weight and overall dimensions in comparison to prototype; connection of modules of compressor units is performed to blowdown plugs of cut-out and current sections of main gas line via additional pipelines and shutoff valves, which allows performing preparatory works and connection to cut-out and current sections of main gas line of mobile compressor station without cutting out the main gas line.
EFFECT: shortening of the time required for gas pumping out of cut-out section of main gas line to current section of main gas line in comparison to prototype.
8 cl, 5 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF GAS PUMPING OUT FROM GAS MAIN SHUT-OFF SECTION AND MOBILE PLANT FOR IMPLEMENTATION OF THIS METHOD | 2017 |
|
RU2661227C2 |
METHOD FOR PUMPING NATURAL GAS OUT OF A DISCONNECTED GAS PIPELINE SECTION | 2022 |
|
RU2785793C1 |
METHOD OF SELECTING GAS OF STARTING, FUEL, PULSE AND FOR INTERNAL REQUIREMENTS FROM TECHNOLOGICAL COMMUNICATIONS OF COMPRESSOR SCHEMES OF COMPRESSOR STATION AS FUEL FOR DISARMING THE RELATED MACHINE TO REPAIR | 2016 |
|
RU2641770C2 |
METHOD FOR MAIN PIPELINE SECTION EMPTYING FROM GAS AND DEVICE FOR IMPLEMENTING IT | 2012 |
|
RU2539411C2 |
GAS PUMPING COMPRESSOR STATION (VERSIONS) | 2014 |
|
RU2543710C1 |
PROCEDURE FOR BLEEDING SECTIONS OF GAS PIPELINES IN MULTI-LINE SYSTEMS OF MAINS | 2010 |
|
RU2426937C1 |
PROCEDURE OF GAS EVACUATION FROM SECTIONS OF PIPLINES IN MULTI-STRAND SYSTEMS OF GAS MAINS (VERSIONS) | 2008 |
|
RU2362087C1 |
PROCEDURE FOR GAS TRANSPORTATION (VERSIONS) AND COMPRESSOR PLANT FOR ITS IMPLEMENTATION (VERSIONS) | 2009 |
|
RU2418991C1 |
PROCEDURE FOR BLEEDING SECTIONS OF GAS PIPELINE IN MULTI-LINE SYSTEMS OF GAS MAINS | 2009 |
|
RU2419738C1 |
GAS PUMPING UNIT AND METHOD OF ITS START-UP | 2014 |
|
RU2607113C2 |
Authors
Dates
2012-10-27—Published
2011-05-23—Filed