FIELD: construction.
SUBSTANCE: method to balance buildings and structures including drilling in soil of wells. A pit is dug at the side of a least sunk part of a building, a structure. The depth of the pit, under which damage starts, is determined with account of maximum depth of well drilling from the foot according to the given dependence. Assembly of rails or guides perpendicularly to a list direction. Assembly of a plant for horizontal drilling of wells. Drilling of horizontal wells of alternating diametre in one row in several stages. The diametre of wells is selected based on structural assumptions and based on possibilities of the drilling plant. Based on the selected dimensions, a pitch of drilling wells, the rated pitch and the diametre of wells is determined according to the calculation based on the pressure value to be pulled when drilling for sight pillar damage, at the same time the damaging pressure is defined using the given dependence.
EFFECT: invention provides for levelling of buildings and structures exposed to uneven deformations of a base without soaking, lower material intensity and labour intensiveness.
3 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR FOUNDATION ENHANCING | 2015 |
|
RU2596621C1 |
0 |
|
SU1670046A1 | |
BUILDING STRAIGHTENING METHOD | 2004 |
|
RU2275474C2 |
METHOD FOR LEVELLING OF BUILDINGS AND STRUCTURES | 0 |
|
SU1818419A1 |
METHOD OF LEVELLING-OUT STRUCTURES | 0 |
|
SU1401110A1 |
TILTED BUILDING STRAIGHTENING METHOD | 2004 |
|
RU2275473C1 |
METHOD FOR STRAIGHTENING OF SLANT IN BUILDING ERECTED ON PILE FOUNDATION | 2008 |
|
RU2382146C1 |
DRILLING METHOD TO ERECT STRIP FOUNDATION IN WATER-BEARING SOILS | 2010 |
|
RU2415228C1 |
METHOD FOR CLUSTER DRILLING OF WELLS | 2014 |
|
RU2593663C2 |
METHOD FOR DEPTH COMPENSATION COMPACTION OF SOIL | 2009 |
|
RU2405890C1 |
Authors
Dates
2012-11-27—Published
2011-07-11—Filed