FIELD: building, particularly for straightening, lifting, or lowering of foundation structures or of constructions erected on foundations.
SUBSTANCE: method involves drilling wells; removing and wetting ground under foundation bed. Wells are drilled in vertical direction in foundation panel of building to be straightened and coaxial injectors are submersed in the wells. Water is injected under pressure through inner cavity of the injectors and ground in the form of sludge is removed through outer injector cavity. Sequence of ground development under foundation panel bed with taking into consideration structure operational conditions are set to exhibit a tendency towards foundation deflecting in both directions, namely in longitudinal and transversal ones. At initial stage amount of removed ground is 0.3-0.8 of total ground amount to be removed to provide building straightening. Then amount of removed ground is increased in according to continuous building settlement data. After heel elimination building position is fixed by supplying high-pressure hardening mixture under foundation bed through above wells.
EFFECT: extended field of application due to possibility of building settlement regulation during foundation panel straightening along with increased safety of building straightening works.
3 cl, 1 ex, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF STRUCTURES ALIGNMENT | 2007 |
|
RU2341621C1 |
METHOD FOR ALIGNMENT OF STRUCTURES | 2007 |
|
RU2346113C1 |
METHOD FOR FOUNDATION ENHANCING | 2015 |
|
RU2596621C1 |
METHOD FOR STRAIGHTENING OF SLANT IN BUILDING ERECTED ON PILE FOUNDATION | 2008 |
|
RU2382146C1 |
METHOD OF HEELING COMPRESSION OF BUILDINGS CONSTRUCTED ON WATER - SATURATED GROUNDS | 2007 |
|
RU2348760C1 |
STRAIGHTENING METHOD FOR BUILDINGS AND BUILDING STRUCTURES ERECTED IN FOUNDATION SLABS | 2006 |
|
RU2318962C2 |
METHOD TO LEVEL BUILDING, STRUCTURE | 2014 |
|
RU2575193C1 |
CORRECTION METHOD OF INCLINATION AND NON-UNIFORM SETTLEMENT OF LARGE HIGH-RISE STRUCTURE AND ITS FOUNDATION | 2010 |
|
RU2436899C1 |
METHOD FOR BUILDING, STRUCTURE ERECTION | 2007 |
|
RU2336391C1 |
METHOD TO CORRECT IRREGULARITIES OF BUILDINGS AND STRUCTURES SUBSIDENCE ON SLAB FOUNDATION | 2011 |
|
RU2468152C1 |
Authors
Dates
2006-04-27—Published
2004-03-29—Filed