FIELD: mining.
SUBSTANCE: all pillar erection operations are performed during winter period after the development of cleaning chamber in alluvial well is completed. A vertical well of large diameter (500-600 mm) is pre-drilled from surface above the developed chamber, under which an underground construction of a moving frame is performed; the above frame is filled with crushed rock mixture formed during summer sand flushing at flushing plants and contained in dumps. Then, mixture is compacted by means of vibration machines and warmed up for a short period of time with its being moistened with superheated steam supplied at high pressure from steam-generating plant in quantity of at least 10 m3 per 1 m of the mixture. After that, frozen rock mixture - pedestal-shaped pillar is frozen in addition with cold air induced with a fan, thus providing high compression properties.
EFFECT: invention allows reducing useful mineral losses and water consumption, increasing pillar erection speed and preventing the deformation of ground surface above developed mine field.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF RAISING ARTIFICIAL PEDESTAL-SHAPED PILLARS IN ALLUVIAL WELLS OF PERMAFROST ZONE | 2015 |
|
RU2601704C1 |
DEVELOPMENT METHOD OF PILLARS OF DRILLED GRAVEL BOREHOLES OF PERMAFROST ZONE | 2010 |
|
RU2436958C2 |
CRYOLITHOZONE RESIDUAL-MONOLITHIC DEEP-BURIED GOLD PLACER DEPOSITS SECONDARY UNDERGROUND TREATMENT ECO-GEOTECHNOLOGICAL METHOD | 2017 |
|
RU2678277C1 |
ECOGEOTECHNOLOGICAL METHOD OF REPEATED UNDERGROUND DEVELOPMENT OF TECHNOGENIC GRAVEL DEPOSITS OF PERMAFROST ZONE | 2009 |
|
RU2428567C1 |
UNDERGROUND DEVELOPMENT METHOD OF TECHNOGENIC DEEP-LYING GRAVEL DEPOSITS OF PERMAFROST ZONE | 2010 |
|
RU2452858C2 |
METHOD FOR CONTAINER-FREE SUBSURFACE BURIAL OF SOLID RADIATION SOURCES IN ABANDONED DEEP WORKINGS OF CRYOLITE ZONE | 2003 |
|
RU2263985C2 |
METHOD FOR FORMING A VENTILATION NETWORK FOR REGULATING THE THERMAL REGIME OF ALLUVIAL MINES IN THE CRYOLITHOZONE | 2020 |
|
RU2749690C1 |
BACKFILLING MASS ERECTION METHOD | 2015 |
|
RU2602565C1 |
METHOD OF PROTECTING LEDGES OF EDGES OF PITS OF CRYOLITHIC ZONE FROM THAWING | 2014 |
|
RU2551583C1 |
METHOD OF ERECTION OF ARTIFICIAL SAFETY ICE-BROKEN PILLARS AT DEVELOPMENT OF DEPOSITS IN CRYOLITE ZONE | 2019 |
|
RU2723317C1 |
Authors
Dates
2013-02-10—Published
2011-02-28—Filed