FIELD: construction.
SUBSTANCE: invention relates to the field of railway construction, in particular to track machines designed for conducting repair works and modernisation of a railway track. A bulk geogrid laying machine in a sub-ballast layer of the railroad track without necessity to remove the rail tie grid contains: a device for lifting the rail tie grid, a device for containing the bulk geogrid, a device for transporting the bulk geogrid under the raised rail tie grid and its stretching to the width specified by the project, a cabin or a control panel, measuring devices.
EFFECT: reduction of cost of the technological process of the track repair and increase of productivity of the bulk geogrid laying are achieved.
12 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
MACHINE TO LAY GEOSYNTHETIC MATERIALS INTO UNDERBALLAST LAYER OF RAILWAY GROUND WORK WITHOUT REMOVAL OF RAIL AND SLEEPER GRID | 2010 |
|
RU2477349C2 |
METHOD TO LAY VOLUME GEOGRID INTO ROAD STRUCTURE, VOLUME GEOGRID AND LAYER FOR LAYING OF VOLUME GEOGRID | 2012 |
|
RU2527392C2 |
MECHANISED METHOD TO LAY GEOSYNTHETIC MATERIALS (GEOTEXTILE AND VOLUME GRATING) INTO ROAD STRUCTURE | 2010 |
|
RU2476634C2 |
MACHINE FOR LAYING OF GEOSYNTHETIC MATERIALS INTO ROADBED AND METHOD OF ITS OPERATION | 2014 |
|
RU2594491C2 |
GEOWEB STACKER WITH EQUIPMENT FOR GEOWEB STORAGE AND STRAIGHTENING AT STACKING | 2012 |
|
RU2505640C1 |
TRACK CONSTRUCTION COMPLEX | 2013 |
|
RU2532311C1 |
METHOD TO REINFORCE RAILWAY TRACK | 2010 |
|
RU2448212C2 |
METHOD TO REPAIR UNDERBALLAST LAYER OF RAILWAY TRACK | 2010 |
|
RU2422579C1 |
TRACK BALLAST CLEANING MACHINE | 2003 |
|
RU2234565C1 |
METHOD TO RESTORE UNDERBALLAST LAYER OF RAILWAY TRACK | 2010 |
|
RU2422578C1 |
Authors
Dates
2014-06-27—Published
2012-06-18—Filed