FIELD: oil and gas industry.
SUBSTANCE: method comprises preparing and cyclic injection of gel-forming agent and liquid glass in the deformation interval. A slurry of ground anhydrite is used as gel-forming agent. The injectability of the insulated interval is pre-determined, and a ground anhydrite slurry is prepared in fresh water at the water-solid ratio of 0.8-1. Depending on the injectability of the insulated interval, from 1 to 15 cycles of ground anhydrite and liquid glass slurry in the volume ratio of 1:1 is pumped into the isolated borehole. Each cycle includes a 1-5 m3of anhydrite ground slurry with addition of synthetic or basalt fiber in an amount 1-6 kg per1 m3 anhydrite slurry, 0.5-1 m3 buffer from fresh water,1-5 m3 liquid glass. Next, cement solution is pumped, dissolved from 2-5 tons of plugging portland cement. The well is left to respond for 24 hours. The diameter of the synthetic or basalt fiber is 10-35 mcm, and its length is 3-18 mm. Fiber is added during preparing or pumping of ground anhydrite slurry.
EFFECT: improved efficiency of the repair and insulation operations method, improved plugging capability and hardening of the obtained plugging stone with the use of a gel-forming agent.
1 tbl
Title | Year | Author | Number |
---|---|---|---|
METHOD OF REPAIR-INSULATION WORKS IN WELL (VERSIONS) | 2015 |
|
RU2599154C1 |
METHOD FOR DOING REPAIR-ISOLATION WORKS UNDER CONDITIONS OF INTENSE ABSORPTION | 2009 |
|
RU2405926C1 |
WATER INFLOW ZONES CEMENTING METHOD | 2013 |
|
RU2533997C1 |
COMPOUND FOR ISOLATION OF WATER INFLOW AND ABSORBING ZONES IN WELL, AND ITS APPLICATION METHOD | 2011 |
|
RU2483093C1 |
METHOD OF WELL WATER PRODUCTION ZONE ISOLATION | 2012 |
|
RU2504640C1 |
METHOD FOR REPAIR INSULATION WORK USING SUSPENSIONS OF FINE MINERAL BINDER | 2015 |
|
RU2582143C1 |
METHOD FOR LIQUIDATION OF ABSORPTION ZONES IN WELL | 2010 |
|
RU2405927C1 |
INSTALLATION METHOD OF BRIDGE CUTTING OFF BELOW-LYING OIL FORMATION | 2012 |
|
RU2494227C1 |
METHOD FOR LIMITING WATER INFLOW IN WELL | 2016 |
|
RU2611794C1 |
PROCEDURE FOR REPAIR-ISOLATION OPERATIONS IN WELL | 2010 |
|
RU2424418C1 |
Authors
Dates
2017-05-04—Published
2016-05-31—Filed