FIELD: construction.
SUBSTANCE: method involves drilling at least two holes in the diaphragms of adjacent superstructure beams along the entire amplified section; installation of strand bundles in holes drilled in the diaphragms; tension and fastening of strand bundles by anchoring elements on the extreme diaphragms; drilling in the upper plates at the joints of adjacent beams, in the area of voids between the diaphragms of the holes, the number of which depends on the number of voids between the diaphragms; formwork under the diaphragms of adjacent beams; filling the voids between the diaphragms with concrete through the holes in the top slabs of adjacent beams and formwork dismantle after the concrete has hardened.
EFFECT: strengthening of the bridge superstructure.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
REINFORCEMENT METHOD OF A BRIDGE STRUCTURE WITH DISMANTLING OF BRIDGE CHANNEL SUPPORTS | 2019 |
|
RU2712984C1 |
METHOD OF RECONSTRUCTION OF THE BRIDGE SPAN STRUCTURE WITH METALLIC DOUBLE-CANTILEVER ARCH | 2018 |
|
RU2689009C1 |
METHOD OF SPRENGEL REINFORCEMENT OF SPAN STRUCTURE | 2023 |
|
RU2804484C1 |
MONOLITHIC SOLID PRESTRESSED PLATE-AND-RIB BRIDGE SPAN STRUCTURE | 2004 |
|
RU2249068C1 |
METHOD FOR RECONSTRUCTION OF REINFORCED CONCRETE BOX-SHAPED SUPERSTRUCTURE IN THE OVERHEAD SECTION OF A BRIDGE | 2022 |
|
RU2801014C1 |
METHOD FOR REINFORCED CONCRETE BRIDGE CONSTRUCTION | 2004 |
|
RU2283911C2 |
METHOD FOR RECONSTRUCTION OF PRESTRESSED REINFORCED CONCRETE BOX-SHAPED STRUCTURE | 2022 |
|
RU2801995C1 |
METHOD FOR TRANSFER OF LONG-SPAN STEAM-AND-WATER MIXTURE DELIVERY PIPELINE OVER CANYON LOCATED IN SEISMICALLY ACTIVE ZONE | 2023 |
|
RU2815705C1 |
METHOD TO MANUFACTURE BEAM OF BRIDGE SPAN | 2013 |
|
RU2528320C1 |
CONSTRUCTION METHOD FOR BRIDGE OR OVERPASS | 2002 |
|
RU2251604C2 |
Authors
Dates
2018-01-12—Published
2016-11-29—Filed