FIELD: construction.
SUBSTANCE: invention relates to waterproofing dowels, more specifically to formwork dowels used in construction of foundations, walls, floor slabs, buried objects, etc. The waterproofing key is made in form of ribbon profile and is characterized by presence of sealing zones with fixing anchors and working area with deformation joint having side walls. The side walls of deformation joint have protruding elements directed towards the formed deformation seam of the structure being erected. The height of side walls protruding elements of deformation joint is greater than the distance from the side wall of deformation joint to the axis of the nearest fixing anchor.
EFFECT: exclusion of cement slurry flow and displacement of waterproofing dowel from its design position during concreting is achieved.
4 cl, 9 dwg
Title | Year | Author | Number |
---|---|---|---|
REPAIR WATERSTOP FOR EXPANSION JOINTS | 2022 |
|
RU2803934C1 |
CONSTRUCTION METHOD OF UNDERGROUND TUNNEL PAVING | 2003 |
|
RU2229000C1 |
PACKAGING UNIT | 2020 |
|
RU2749205C1 |
RETAINED FORMWORK PACKAGE, METHOD OF ITS ASSEMBLY AND METHOD OF CONSTRUCTION OF MONOLITHIC WALLS OF BUILDING AND STRUCTURE IN RETAINED FORMWORK OF MODULAR ELEMENTS | 2013 |
|
RU2561135C2 |
METHOD FOR CREATING JOINT SEAL FOR TEMPERATURE AND TEMPERATURE-SEDIMENTATION OF HYDRAULIC STRUCTURE | 2023 |
|
RU2814951C1 |
METHOD FOR ERECTION AND RECONSTRUCTION OF BUILDINGS AND PRODUCTION OF ARTICLES FROM COMPOSITE MATERIALS MAINLY OF CONCRETE FOR ABOVE PURPOSES | 1996 |
|
RU2107783C1 |
METHOD OF MULTI-STOREY BUILDING LIGHTENED FLOORS INSTALLATION | 2017 |
|
RU2652402C1 |
METHOD FOR ERECTION AND RECONSTRUCTION OF BUILDINGS AND PRODUCTION OF ARTICLES FROM COMPOSITE MATERIALS MAINLY CONCRETE FOR ABOVE PURPOSES | 1996 |
|
RU2107784C1 |
METHOD OF ERECTING BUILDING COVER OR OVERFLY STRUCTURE | 2015 |
|
RU2582682C1 |
METHOD FOR ERECTING SMALL-STOREY BUILDINGS AND DEVICE FOR IMPLEMENTING THE SAME | 1992 |
|
RU2057864C1 |
Authors
Dates
2021-10-18—Published
2021-05-13—Filed