FIELD: miniplants for production of cement and other building materials. SUBSTANCE: plant comprises functional units located in sequence of the process for preparation and processing of raw material mixture and transportation facilities interconnected the units. Plant is made in the form of airtight module which accommodates units and transportation facilities. Units are accommodated in airtight housings or casings, and transportation facilities are found in pipelines tightly connected with bodies of respective units. Such design of plant reduces to minimum the effluents of cement and production dust to environment. EFFECT: higher efficiency. 1 dwg
Title | Year | Author | Number |
---|---|---|---|
PORTLAND CEMENT PRODUCTION METHOD AND PORTLAND CEMENT BASED CONCRETE AND REINFORCED CONCRETE PIECES PRODUCTION METHOD | 1995 |
|
RU2060979C1 |
METHOD OF FINE-GRAINED OIL SHALE PYROLYSIS TO PRODUCE LIQUID AND GAS FUELS, ELECTRIC POWER AND CEMENT CLINKER, AND DEVICE TO THIS END | 2008 |
|
RU2423407C2 |
METHOD OF MANUFACTURING CEMENT CLINKER | 1995 |
|
RU2097350C1 |
TECHNOLOGICAL SYSTEM FOR PRODUCTION OF CEMENT | 0 |
|
SU1732127A1 |
METHOD OF FABRICATING CEMENT CLINKER | 1995 |
|
RU2083518C1 |
METHOD FOR MANUFACTURING OF PORTLAND CEMENT AND FERROCONCRETE ARTICLES ON THE BASE OF PORTLAND CEMENT | 1995 |
|
RU2060978C1 |
PRODUCTION OF HIGH-STRENGTH HIGH-EARLY-STRENGTH ALITE PORTLAND CEMENT AND PRODUCTION LINE TO THIS END | 2012 |
|
RU2520739C2 |
METHOD FOR PRODUCTION OF PORTLAND CEMENT (VERSIONS) | 2008 |
|
RU2383506C1 |
METHOD FOR THERMAL PROCESSING OF SLATE COAL WITH PRODUCTION OF LIQUID AND GASEOUS FUEL AND ALSO CEMENT CLINKER AND FACILITY FOR ITS EMPLOYING | 2007 |
|
RU2339673C1 |
PROCESSING LINE FOR PROCESSING ASH-SLAG WASTES FROM DUMPS OF ASH REMOVAL SYSTEMS OF THERMAL POWER PLANTS IN ORDER TO OBTAIN STANDARD ASH PRODUCTS | 2018 |
|
RU2700608C1 |
Authors
Dates
1997-12-20—Published
1995-03-24—Filed