FIELD: construction.
SUBSTANCE: main cross beam is mounted, a pair of beam balancers covering column at both sides and balancing on the main traction rods are suspended to cross beam ends at main traction rods hanging along sides of emergency cantilever. Short arms of this pair of balancers are brought and rested at the bottom under supports of adjacent crane beams, and long arms of this pair are rested at the bottom against ends of thrust beams protruding beyond sides of column via adjustment nuts of traction rods. Accordingly middle parts of these beams are rested at the bottom against fixed supports of angles welded to bare working reinforcement of column at its back side. In gap between crane beams and near front face of upper part of column, next to centre of gravity of lower part of column, basement is locally fixed, and low modular pad is rested against it, for instance, from conveyor belt.
EFFECT: full recovery of building carcass column serviceability without interruption of production process.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR UNLOADING DETERIORATING REINFORCED-CONCRETE CANTILEVERS | 2006 |
|
RU2346878C2 |
METHOD FOR COMPLETE UNLOADING OF REINFORCED CONCRETE CANTILEVER OF COLUMN AGAINST ACTION OF CRANE BEAMS | 2011 |
|
RU2469948C2 |
METHOD TO RECOVER BEARING CAPACITY OF PILLARS OF REINFORCED CONCRETE SYMMETRICAL CANTILEVERS THAT ARE DAMAGED IN MIDDLE ROW | 2010 |
|
RU2477776C2 |
METHOD OF DAMPING OVERHEAD CRANE EFFECTS AND UNLOADING REINFORCED-CONCRETE SUPPORT OF COLUMN DISINTEGRATING FROM CONCRETE REINFORCEMENT CORROSION | 2010 |
|
RU2457998C2 |
METHOD OF COMPLETE RELIEF OF COLUMN REINFORCED CONCRETE CANTILEVER | 2011 |
|
RU2496709C2 |
METHOD OF COMPLETE RECOVERY OF SERVICEABILITY OF DANGEROUS COLUMN REINFORCED CANTILEVER TAKING UP BEARING REACTIONS OF ADJACENT CRANE GIRDERS | 2012 |
|
RU2496708C2 |
CANTILEVER OF REINFORCED CONCRETE COLUMN | 2002 |
|
RU2233955C2 |
METHOD TO MANUFACTURE GUNCRETE ELEMENTS OF STEEL DOUBLE-BRANCH PILLAR | 2011 |
|
RU2477773C1 |
CRANE RUNWAY STRENGTHENING METHOD | 1994 |
|
RU2114045C1 |
CRANE RUNWAY BEAM-TO-COLUMN CONNECTION UNIT | 1998 |
|
RU2188153C2 |
Authors
Dates
2011-03-27—Published
2008-11-17—Filed