FIELD: construction.
SUBSTANCE: method to install a continuous welded rail consists in the fact that a rail is laid with its foot onto rollers installed on a slab track, its one end is connected to a previously laid rail, a longitudinal force is applied to its other end as adjustable in value. The rail laid onto rollers is heated, rollers are removed, and the rail is fixed on the slab track. At the same time the start section of the rail is heated until it is fully laid onto the rollers, and the start control sections of the rail are extended to the rated length.
EFFECT: increased efficiency due to provision of identical values that correspond to the recommended temperature of rail fixation for the permanent mode of operation along the whole length of the installed rail.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD OF LAYING CONTINUOUS WELDED RAIL TRACK SLEEPER-AND-RAIL SECTION | 2012 |
|
RU2500850C1 |
METHOD OF PUTTING LAID RAIL LENGTHS OF CONTINUOUS WELDED RAIL TRACK INTO OPERATION AND RAIL SLIDES FOR IMPLEMENTING THE METHOD | 2006 |
|
RU2322542C2 |
METHOD FOR UNINTERRUPTED PATH STRINGS LAYING WITH THEIR EXTENSION, BY WELDING AND ENTERING INTO OPTIMAL FIXATION TEMPERATURE | 2019 |
|
RU2732635C1 |
METHOD OF LAYING CONTINUOUS WELDED RAIL LENGTHS | 1997 |
|
RU2112103C1 |
METHOD OF REMOVING THERMAL STRESS IN CONTINUOUS WELDED TRACK RAIL-AND-TIE ASSEMBLY | 2011 |
|
RU2472894C1 |
METHOD OF LAYING CONTINUOUS WELDED RAIL TRACK SLEEPER-AND-RAIL SECTION | 2013 |
|
RU2541618C1 |
METHOD FOR LENGTHENING OF LONG STRINGS OF CONTINUOUS WELDED RAIL TRACK | 2012 |
|
RU2520178C2 |
METHOD TO ELONGATE JOINTLESS TRACK RAILS | 2009 |
|
RU2388864C1 |
METHOD OF RELIEVING STRESS IN RAIL FRAME OF JOINTLESS TRACK | 2009 |
|
RU2399714C1 |
METHOD TO EXTEND CONTINUOUS WELDED RAIL TRACK LENGTHS | 2011 |
|
RU2495975C2 |
Authors
Dates
2011-12-27—Published
2010-02-15—Filed