FIELD: mining.
SUBSTANCE: erection method of a liner of inclined or horizontal shafts provides for construction in the inclined or horizontal shaft of the mine working of a supporting frame with scaffolding for performance of work, which forms at least two parts corresponding to the arch surface. The following is performed during work execution: anchors are installed, which fix the frame in the mine working shaft; a set of screw turnbuckles determining the design position of the arch is fixed on the scaffolding and in upper part of the arch bottom; a set of jacks determining the design position of the arch is fixed on the scaffolding and in the lower part of the arch bottom. A sheet bottom of the arch is fixed on the supporting frame; a shield bottom of a tray is suspended on movable beams of the supporting frame; laying of concrete mixture, dismantling of the formwork and movement of the supporting frame in inclined or horizontal shaft of the mine working is performed.
EFFECT: improving erection quality of horizontal mine workings owing to improving location accuracy of a formwork and due to quality of concrete application onto the shaft surface.
2 cl, 2 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR ERECTION OF STEEL CONSTRUCTIONS OF VERTICAL MINE OPENING SHAFT AND ARMORING UNIT FOR IMPLEMENTATION OF THE METHOD | 2014 |
|
RU2601647C2 |
ERECTION METHOD OF EARTHQUAKE RESISTANT CONCRETE SUPPORT | 2012 |
|
RU2509893C1 |
METHOD TO LAY CONCRETE BEHIND TUBBING LINING OF VERTICAL MINE AND COMPLEX OF EQUIPMENT FOR REALISATION OF METHOD | 2012 |
|
RU2514338C1 |
METHOD TO CONSTRUCT VERTICAL MINE BY BLASTING AND DRILLING METHOD WITH TUBING LINING AND TUNNELLING COMPLEX FOR METHOD REALISATION | 2012 |
|
RU2493367C1 |
ALL-PURPOSE MODULAR FORM ASSEMBLY | 2005 |
|
RU2282700C1 |
DEVICE FOR ERECTION OF UNDERGROUND STRUCTURE FROM CAST-IN-SITU PRESSED CONCRETE | 1999 |
|
RU2166091C1 |
METHOD AND APPARATUS FOR MAKING LININGS OF UTILITY TUNNELS | 0 |
|
SU1752969A1 |
SINGLE-VAULT DEEP UNDERGROUND STATION WITH SUPPORTING TUNNELS, CONSTRUCTED BY A CLOSED METHOD FOR WORK | 2022 |
|
RU2785300C1 |
METHOD TO TUNNEL HORIZONTAL OR INCLINED UNDERGROUND MINE AND TUNNELLING MACHINE FOR METHOD REALISATION | 2011 |
|
RU2490467C2 |
METHOD OF ERECTING UNDERGROUND STRUCTURE VAULT | 0 |
|
SU1758235A1 |
Authors
Dates
2014-03-27—Published
2012-09-18—Filed