FIELD: construction.
SUBSTANCE: method of soil reinforcement may be used in strengthening and arrangement of bases with any soil conditions, in particular, weak natural bases and unsteady soils. A contour of reinforced concrete support falsework is defined, within the borders of which they install a set of at least three longitudinal hollow elements that represent a tubular-pillar falsework, and they are submerged into soil. On shore they determine the sufficient quantity of reinforcement zones. Piles are placed in each of specified elements, a reinforcement zone, under different angles to the surface of the specified support and with protrusion of each pile beyond the border of the lower perimeter of the appropriate element with formation of vectors of forces that compensate load at specified soils. Along the formed contour they assemble the falsework that covers upper heads of piles, they fill the longitudinal hollow elements with concrete and form the reinforced concrete support.
EFFECT: increased strength of a soil base due to installation of piles and increased area of their resting against soil with simultaneous reduction of labour intensiveness and material intensity.
3 cl, 3 dwg
Title | Year | Author | Number |
---|---|---|---|
PROCESS OF CONSOLIDATION OF WATER-SATURATED GROUND IN FOUNDATIONS OF BUILDINGS AND STRUCTURES | 2002 |
|
RU2204650C1 |
METHOD OF MANUFACTURING OF BEARING COMBINED REINFORCED IN SITU PILE | 2007 |
|
RU2334048C1 |
CORRECTION METHOD OF INCLINATION AND NON-UNIFORM SETTLEMENT OF LARGE HIGH-RISE STRUCTURE AND ITS FOUNDATION | 2010 |
|
RU2436899C1 |
METHOD FOR STRENGTHENING STRUCTURALLY UNSTABLE SOILS WITH KARST FORMATIONS AND/OR WATER-SATURATED SOILS USING MICROPILES AND INJECTORS FOR FORMING MICROPILES | 2022 |
|
RU2795924C2 |
PIPE CONCRETE PILE WITH REINFORCED BASE AND METHOD OF ITS ERECTION | 2011 |
|
RU2492294C1 |
METHOD TO REINFORCE DEFECTIVE LINING OF TUNNEL | 2012 |
|
RU2511168C1 |
METHOD TO PREVENT DEFORMATIONS OF LINEAR STRUCTURES ERECTED ON LANDSLIDE SLOPES OR MANMADE SLOPES ON MELTING PERMAFROST SOILS | 2014 |
|
RU2556646C1 |
METHOD FOR STRENGTHENING OF SLOPES AND SLOT MAKER FOR ITS REALISATION | 2008 |
|
RU2371547C1 |
ICE BERTH | 2021 |
|
RU2764806C1 |
COMPLEX FOR CONSTRUCTION OF MOTOR ROAD ON PILES | 2010 |
|
RU2453650C1 |
Authors
Dates
2014-04-20—Published
2012-08-22—Filed