FIELD: construction.
SUBSTANCE: invention relates to construction in regions with complex engineering and geocryological conditions and can be used for stabilization of permanently frozen and freezing of weak plastic frozen soil. Installation method of light cooling devices for temperature stabilization of permanently frozen grounds includes drilling through flat-dipping well drawing cooling device equipped with pipes of evaporator and condenser connected bellows sleeves, protected bands, to the well to design position, installation of cooling elements on the condenser pipe cooling device. Cooling device previously laid in protective holder consisting of casing pipes of coupling connection, both end faces of which are equipped with damping gaskets and screwed covers, drawn to the well to the design mark with simultaneous expansion of the well. Protective shell is removed from condensing sections of pipes of the cooling device, and the pipes are attached with anchors. In the gap between the protective case and well walls installed cementing pipe and the drilling machine protective holder with simultaneous supply of cement mortar with water/cement ratio W:C=0.5 in clearance between the cooling device and the walls of the well.
EFFECT: increasing carrying capacity of soil bases, reduced load of structures on light-weight design of heat stabilizers, low material consumption for construction and erection works.
1 cl, 5 dwg
Title | Year | Author | Number |
---|---|---|---|
COOLING DEVICE FOR TEMPERATURE STABILISATION OF PERMAFROST SOILS AND METHOD TO INSTALL SUCH DEVICE | 2010 |
|
RU2454506C2 |
METHOD FOR ASSEMBLING COOLING DEVICES FOR TEMPERATURE STABILIZATION OF PERMAFROST SOILS UNSTABLE IN WELL WALLS | 2016 |
|
RU2634315C1 |
HEAT SETTING OF GROUNDS | 2016 |
|
RU2661167C2 |
SOIL THERMAL STABILIZER WITH UNDERGROUND VERSION OF CONDENSER PART | 2023 |
|
RU2816611C1 |
METHOD OF INSTALLING HEAT STABILIZERS IN VENTILATED UNDERGROUND OF OPERATED BUILDINGS | 2016 |
|
RU2627793C1 |
METHOD OF DRILLING INJECTION PILE | 2023 |
|
RU2817842C1 |
METHOD OF REINFORCING THAW ZONES AT BASE OF STRUCTURES | 2024 |
|
RU2824869C1 |
METHOD OF CONSTRUCTION AND INSTALLATION OF PILES IN PERMAFROST ZONES USING HEAT STABILIZATION COUPLINGS | 2023 |
|
RU2818341C1 |
METHOD FOR DEPTH COMPENSATION COMPACTION OF SOIL | 2009 |
|
RU2405890C1 |
PILE AND METHOD OF ITS INSTALLATION INTO PERMAFROST SOIL | 2010 |
|
RU2441116C1 |
Authors
Dates
2016-07-20—Published
2015-05-27—Filed