FIELD: construction.
SUBSTANCE: invention relates to construction and can be used in erecting pile-plate foundations that take up horizontal force. Pile-plate foundation comprises piles installed from the bottom of the pit, combined with a grill plate. It is assemblable to take up horizontal force, and the foundation contains piles, made with a square section with longitudinal rectangular grooves on the faces in the upper part of the piles above the foundation of the pit. Upper parts of the piles, located in the pit, further combined by diaphragms installed in said grooves, and forming a closed structure in the form of a cell or a grid of cells. Grill plate is formed by assemblable plates, laid on the piles and diaphragms to combine them by welding the reinforcement and concreting.
EFFECT: technical result is simplified technology of erection and reduced duration of the process by performing a assemblable structure with increased rigidity of the above-ground part and taking up horizontal force.
4 cl, 4 dwg
Title | Year | Author | Number |
---|---|---|---|
METHOD FOR SLAB-AND-PILE FOUNDATION ERECTION | 2006 |
|
RU2305154C1 |
METHOD TO ERECT PILED RAFTS | 2013 |
|
RU2548461C1 |
CONSTRUCTION OF PREFABRICATED GROUND FOUNDATION FOR HIGH-SPEED RAIL TRANSPORT OVERPASS | 2023 |
|
RU2814450C1 |
BAND-SHELL SHALLOW FOUNDATION | 2018 |
|
RU2689957C1 |
METHOD FOR PILE-AND-SLAB FOUNDATION CONSTRUCTION IN SEISMIC AREAS | 2005 |
|
RU2300604C1 |
METHOD FOR PILE-AND-MAT FOUNDATION ERECTION | 2006 |
|
RU2321703C1 |
METHOD FOR PLATE-PILE FOUNDATION CONSTRUCTION | 2016 |
|
RU2616633C1 |
FOUNDATION OF PILES AND SLABS | 2007 |
|
RU2331738C1 |
PREFABRICATED BLOCK OF FERROCONCRETE MAT OF PILE FOUNDATION AND METHOD OF CONSTRUCTING PILE FOUNDATION WITH FERROCONCRETE MAT OF PREFABRICATED BLOCKS | 0 |
|
SU1135852A1 |
TECHNIQUE FOR ERECTING SOLID CORE FOUNDATION SLAB | 2006 |
|
RU2325483C1 |
Authors
Dates
2018-04-02—Published
2016-12-29—Filed