FIELD: railroad track facilities mechanization, particularly to assemble railroad lengths at manufacturing facilities of machine stations.
SUBSTANCE: production line comprises sleeper preparation section to prepare sleepers to further assemblage. The sleeper preparation section includes process stations, which lay sleeper in row and in accordance to epure and supply fastening members. Rail length assemblage section is parallel to sleeper preparation section. The rail length assemblage section includes process stations, which lay rails on sleepers and finally assemble railroad lengths. Production line also has satellite carts sliding along power-driven rollers so that the carts may be articulated to each other to create launder. Sleeper preparation section has sleeper centering device, which aligns sleepers with rail pads and located out of sleeper laying station. Transversal conveyers are arranged between parallel sections at ends thereof. The rail length assemblage section comprises rail-receiving means with rail grips and provides rail orientation along rail pad during successive rail lowering on sleepers. In rail laying area sleepers are arranged on launder including separate satellite carts.
EFFECT: increased efficiency and uniformity of technological equipment operation and possibility to mount the production line inside working area due to decreased production line size.
1 dwg
Title | Year | Author | Number |
---|---|---|---|
FLOW LINE TO ASSEMBLE RAIL LENGTHS | 2009 |
|
RU2410484C2 |
METHOD TO ASSEMBLE RAIL LENGTHS IN UNPADDED TYPE OF JOINTS | 2010 |
|
RU2437979C1 |
RAIL LENGTH ASSEMBLY LINE | 2008 |
|
RU2377357C1 |
PRODUCTION ASSEMBLY LINE OF TRACK SWITCHES | 2008 |
|
RU2385373C1 |
FLOW LINE FOR ASSEMBLY OF RAIL-AND-SLEEPER GRID LINKS IN RAILWAY TRACK | 2008 |
|
RU2373320C1 |
PRODUCTION LINE FOR RAILROAD LENGTH ASSEMBLAGE | 2005 |
|
RU2304190C1 |
PRODUCTION LINE FOR REPAIR OF ASSEMBLED RAIL AND SLEEPER LINKS | 2010 |
|
RU2443825C1 |
FLOW LINE FOR ASSEMBLING RAILWAY TRACK SECTIONS | 2004 |
|
RU2260089C1 |
PRODUCTION ASSEMBLY LINE OF LINKS OF TRACK SKELETON OF RAILROAD | 2010 |
|
RU2436886C1 |
LINE FOR REPAIR OF RAILWAY TRACK LENGTHS WITH REINFORCED CONCRETE TIES | 2007 |
|
RU2361032C1 |
Authors
Dates
2007-08-10—Published
2006-04-03—Filed