FIELD: oil and gas industry.
SUBSTANCE: method includes increasing the upper bearing surface area of the pile. A recess is made around the strengthened pile pier within a radius of 1.5 to 2.5 of the outer diameter of the pile (Dc) with a depth equal to the thickness of the necessary concrete layer. A reinforcing frame is mounted into the recess and the recess is filled with concrete. A metal support structure with reinforcing ribs is installed after concreting and fixedly connected to the aboveground part of the pile.
EFFECT: increased bearing capacity of the pile pier which is already installed and operated in the areas of permafrost soil by increasing the bearing surface area of the pile carried out at the daylight surface level.
2 dwg
Title | Year | Author | Number |
---|---|---|---|
MULTI-PILE FOUNDATION AND METHOD FOR ERECTION THEREOF ON FROZEN SOILS | 2015 |
|
RU2584019C1 |
METHOD FOR PROTECTING THE BEARING SUPPORT STRUCTURE OF ABOVE-GROUND MAIN PIPELINE FROM THE IMPACT OF THE FORCES OF FROSTY HEAVING OF SOIL | 2022 |
|
RU2785329C1 |
METHOD FOR CONSTRUCTING DRILLED PILE IN PERMAFROST SOIL | 2023 |
|
RU2803751C1 |
PILE FOUNDATION FOR SEISMIC TERRITORIES | 2005 |
|
RU2307212C2 |
PIPE CONCRETE PILE WITH REINFORCED BASE AND METHOD OF ITS ERECTION | 2011 |
|
RU2492294C1 |
METHOD FOR SLAB-AND-PILE FOUNDATION ERECTION | 2006 |
|
RU2305154C1 |
FOUNDATION OF RECONSTRUCTED BUILDING | 2010 |
|
RU2431718C1 |
METHOD OF SOIL REINFORCEMENT | 2012 |
|
RU2513954C2 |
METHOD FOR RESTORING BUILDINGS WITH A VENTILATED UNDERGROUND AFTER THAWING OF THE FOUNDATION SOILS | 2021 |
|
RU2771359C1 |
COMBINED METHOD OF ARRANGEMENT OF PILE FOUNDATIONS IN PERMAFROST SOILS | 2019 |
|
RU2712976C1 |
Authors
Dates
2017-05-22—Published
2016-03-10—Filed