FIELD: metallurgy.
SUBSTANCE: method involves shot-blasting treatment of working copper surface of tuyere, application thereto of aluminium-bearing gas-thermal coating, and heat treatment which involves the furnace tuyere heating up to 780-800°C, exposure during 4-10 h and cooling in the furnace. Thickness of coating on external surface of tuyere is 0.5-0.6 mm, and it exceeds the thickness of coating on its external surface by not less than 40% on surface of blasting channel of tuyere.
EFFECT: reduction of the number of treatment operations of air tuyere surface.
4 ex, 1 tbl
Title | Year | Author | Number |
---|---|---|---|
BLAST FURNACE TUYERE PREPARATION METHOD | 2008 |
|
RU2387716C2 |
METHOD FOR PREPARING AIR TUYERE OF BLAST FURNACE FOR OPERATION | 2004 |
|
RU2260058C1 |
METHOD OF PREPARING TO OPERATION AND INSTALLATION OF BLAST FURNACE AIR TUYERE | 2006 |
|
RU2327742C2 |
METHOD OF PREPARATION OF BLAST FURNACE AIR TUYERE FOR OPERATION | 2006 |
|
RU2325444C2 |
METHOD OF PREPARATION OF BLAST FURNACE TUYERE FOR OPERATION | 2001 |
|
RU2215043C2 |
BLAST TUYERE FOR BLAST FURNACES AND METHOD OF MANUFACTURE OF SUCH TUYERE | 2002 |
|
RU2233338C1 |
METHOD FOR PREPARING OF BLAST FURNACE TUYERE FOR OPERATION | 2005 |
|
RU2308491C2 |
METHOD FOR PREPARING BLAST FURNACE TUYERE FOR OPERATION | 1998 |
|
RU2147614C1 |
METHOD OF PREPARATION FOR OPERATION OF BLAST-FURNACE TUYERE | 1997 |
|
RU2115740C1 |
BLAST TUYERE OF BLAST FURNACE AND METHOD FOR APPLYING OF PROTECTIVE COATING ONTO BLAST TUYERE OF BLAST FURNACE | 2002 |
|
RU2235789C2 |
Authors
Dates
2012-10-27—Published
2011-02-04—Filed